Chart gantt Effort & Cost

  • My effort calculations are resulting in partial workdays, will this cause any issues?
Whilst Microsoft Excel does not support partial workdays, Chart Gantt Does!  We have coded around the issues associated with Microsoft's workday function "forgetting" partial workdays.  Chart gantt will faithfully display a 4.25 workday task as 4 days, plus a part of the second day.  As the lowest level of graphical capability in Chart gantt is the day, 5 workdays are displayed rather than 4.